Recent deliveries, what's underway now, and what's planned next — drawn from the council's own plans, budgets and project pages. We report what the council has publicly said it's doing; every item links to its source.
The council's stated direction
Griffith City Council's direction is set out in its Community Strategic Plan ('We are Griffith 2025–2035') and a Delivery Program 2025/26–2028/29 with an annual Operational Plan and budget, focused on the region's agribusiness economy, water security and growing the regional centre.
The council manages local roads, water and waste, libraries, parks, an art gallery, a regional theatre and airport, and planning across a large, mostly rural LGA anchored by the town of Griffith in the Murrumbidgee Irrigation Area. Its Delivery Program is the elected council's statement of commitment for its term.
The Delivery Program funds the council's annual capital works program; a two-year Special Rate Variation (2024–25 and 2025–26) was approved by IPART to lift rates income toward infrastructure and service costs.
Underway now
Griffith Regional Airport Master Plan
Master plan commenced 2026; framework spans 10–20 yearsThe council appointed aviation consultancy To70 to develop a new Master Plan for Griffith Regional Airport, providing a strategic framework for future airport development, infrastructure, land use and investment. Project activities and initial stakeholder engagement began in July 2026.
Source: Griffith City Council — Griffith Regional Airport Master Plan project underway
Griffith City Beautification & Tourism Enhancement (CBD & Lake Wyangan)
$4M project; concept endorsed Dec 2025A $4 million project — $3 million from the NSW Sustainable Communities Program plus $1 million from the council — to improve the Lake Wyangan foreshore and enhance the Griffith CBD. The concept design was endorsed by the council in December 2025 and community feedback was sought into early 2026.
Source: Connect Griffith — Griffith CBD Enhancement Project (Invigorate Griffith)
Planned / committed
We are Griffith 2025–2035 Community Strategic Plan
to 2035The council's top-level Community Strategic Plan setting long-term goals for the economy, environment, infrastructure and community wellbeing across the LGA.
Source: Connect Griffith — Community Strategic Plan 2025–2035